PASSENGER
FERRY LANDING AT NORTH WILLIAMSBURG – NEW YORK CITY ECONOMIC
DEVELOPMENT CORPORATION (NYCEDC)
Construction of a 35’ x 75’ barge anchored with four
spud piles. Installation of two bowloader ramps and a gangway to
the existing pier as well as installation of four monopoles with
donut fenders.
16,000 TONS THROGS NECK ORTHOTROPIC BRIDGE
Fabrication for installation on the Throgs Neck Bridge, NYC. Delivery,
via water, utilizing barges, handling 1200 panels weighting 38 tons
each.
RIVERSIDE VIADUCT REHABILITATION
From 125th Street to 134th Street, New York City –NYSDOT Contract,
Subcontract to American Bridge, Approx. 1800 tons, drilled and bolted
connection.
TWO (2) TANK DIGESTER TANK COVERS
Approx. 40 tons each, 62’ diameter. One piece tank covers
for Yonkers Sewage Treatment Plant, City of Yonkers, New York.
FOUR (4) FLOATING 1200 TON CONCRETE CAISSONS
Forming and pouring transformer vaults for installation at U.S.
Naval Station, Staten Island, NY, Battleship Iowa. Poured at Steel
Style Shipyard facilities, Newburgh, NY and floated into position.
CONSTRUCT BRIDGE & DEMOLISH NEWBURGH
TUNNEL & RELATED WORK
Newburgh, NY, Consolidated Rail Corporation. A high profile Conrail
pile driven, welded bridge construction including the demolition
of a 500’ active main line rail tunnel.
FIFTY-FOUR (54) SEMI-PORTABLE 20’
VANDAL PROOF, ALL STEEL MINI POOLS
New York City Department of Parks, Recreation, and Cultural Affairs.
Corona Park, NY
PONTOON LAUNCHER
Trident Submarine Launch Facility, Groton, CT. Fabricated for General
Dynamics Corp., Electric Boat Division. Vessel weighing approximately
6,000 tons, measures 100’W x 500’L.
FLOATING CAISSON GATE
Trident Submarine Launch Facility, Groton, CT. Fabricated for Morrison-
Knudsen Co., the prime contractor and General Dynamics Corp. Electric
Boat Division.
FOUR (4) STEEL CAISSONS
66’W x 107’L x 175’H - For the second Newburgh-Beacon
Bridge, fabricated for the Joint Venture of Steers-Spearin-Yonkers-Buckely,
the prime contractor.
DRYDOCK CAISSON GATES- FOR THE FOLLOWING
U.S. NAVY SHIPYARDS
• Drydock No. 1 Caisson Gate, Charleston Naval Shipyard, Charleston,
SC,
• Drydock No. 4 Caisson Gate, Norfolk Naval Shipyard, Portsmouth,
VA.
• Drydock No. 1 Caisson Gate, Pearl Harbor Naval Shipyard,
Pearl Harbor, Hawaii.
NEW YORK CITY DEPARTMENT OF SANITATION
BARGE
Clean Water II, Freshkills Marine Unloading Plant # 1, Freshkills,
Staten Island.
TWO CRANE BARGES
65’W x 120’L x10’H and 65’W x 160’L
x 12’H - For Weeks Stevedoring Company, Inc. 216 North Avenue
East, Cranford, NJ 07016.
ELEVEN (11) COVERED LIGHTERS
(YFN) and two (2) Open Lighters (YC) (32’W x 110’L x
9’H) for Naval Sea Systems Command, Washington, D.C.
STEEL ROOF TRUSS AND PLATE COVER
For two (2) 36 million gallon Liquified Natural Gas Tanks, 135’
high x 283’ diameter, fabricated and erected for Walsh Construction
Co., 711 Third Avenue, New York, NY. The tanks represent the largest
of their type ever constructed.
CONSTRUCT WALERS, CHANNEL CAPS, HANDRAILS
AND RELATED PARTS
For the reconstruction of the Cold Spring Dock, in Cold Spring,
NY (a portion of the Corps of Engineers Superfund cleanup of the
marathon Battery site), International Technology Corporation.
MAINTENANCE DREDGING AND RELATED WORK
Norrie Point Marina, M.L. Norrie State Park, Staatsburg, NY. Dredge
marina harbor and other related work, 12,850 cubic yards of material,
New York Office of Parks Recreation and Historic Preservation.
DREDGING OF HAZARDOUS MATERIALS
Marathon Battery Superfund Site, Cold Spring, NY- Dredge 2,200 cubic
yards of contaminated material at the Cold Spring Dock, Sevenson
Environmental Services, Inc.
121’ X 40’ 12’ STEEL
PONTOON FOR THE CHILDREN’S MUSEUM BOSTON, MA
A steel pontoon, 130 tons, to support a three story floating museum.
General Contractor: Barr & Barr, Inc.
*Some projects were completed under
Steel Style, Inc., a former related party.
|